The responsible person | Time | |
---|---|---|
1
The admission for consideration of the application for granting the relevant rights to the land
|
The initiator | 1 working day |
2
Definition of possibility of use of the claimed land by the declared purpose in accordance with the territorial zoning (Making the act of choosing a land plot)
|
10 working days | |
3
A preliminary selection of a land plot (in case of purchase of land for construction, except construction of facilities within the settlement)
|
5 working days | |
4
Preparation of conclusion by the Commission created by the relevant local Executive bodies on granting of a land plot
|
10 working days | |
5
The development and approval of land management project
|
||
6
The decision of the local Executive body of oblast, city of Republican significance, capital, district, city of oblast subordinance, akim of city of district significance, settlement, village, rural district on grant of right to land plot (the Decision/Resolution of Akimat
|
Akimat/district | 7 working days (copy of the Decision sent to the applicant within 5 days) |
7
The conclusion of the contract of purchase and sale or temporary (short term, long term) compensated (uncompensated) land use
|
The authorized body region | No later than 10 working days from the date of the decision |
8
The establishment of land boundaries on the ground
|
The initiator | 10 working days |
9
Production and issuance of identification document for land plot, with the exception of the land plot intended for construction of facilities within the village
|
A public Corporation, leading the state land cadastre | 6 working days |